Neighbors for Wintersburg Wetlands Restoration

17451 Hillgate, Huntington Beach, CA 92649-4707 - 714-625-0876 - www.bixby.org/parkside

__________________________________________________________________

 

September 19, 2002

 

City of Huntington Beach

Department of Planning

Planning Commission

2000 Main St.

Huntington Beach, CA  92648

 

 

RE: Parkside Estates

 

Dear Planning Commission,

 

I am writing to you regarding various Parkside Estates issues that remain unresolved as we head into the September 24th continuation meeting.  We believe that the EIR should not be certified at this time because of multiple serious deficiencies.  Furthermore, if these deficiencies are someday corrected and the EIR is eventually certified, there are various changes we would like to see in the conditions for the project.

 

1. Justification for Re-opening the Public Hearing

 

Although the public hearing was closed at the conclusion of the Parkside agenda item on September 10th, we feel the hearing needs to be re-opened on September 24th due to the following reasons:

 

  • Distribution of the September 10th staff reports was botched and they did not appear in the HB central library until Monday September 9th.  Several residents attempted to view the staff reports at the library over the preceding weekend but were unsuccessful because the reports were not yet available at the Reference desk.

 

  • The updated traffic study was released on September 9th, leaving insufficient time for thoughtful public analysis prior to the September 10th public hearing.

 

  • There was significant new California Coastal Commission and Rivertech water quality correspondence released on September 9th and 10th, leaving insufficient time for thoughtful public analysis prior to the September 10th public hearing.

 

  • Planning Commissioners had many unresolved questions at the conclusion of the September 10th public hearing, and asked that staff provide answers in writing.  The public needs a chance to review these same answers and to comment on any errors or omissions therein.

 

2. Problems with the September 9, 2002 Traffic Study

 

While it is gratifying to see that our concerns with the stale traffic data in the July 2002 Final EIR were taken seriously enough to warrant the new traffic study dated September 9, 2002, the timing and content of this new study raise some significant new issues that we believe allow us to challenge the validity of this new study, too.

2.1 Some Data Collected BEFORE School Resumed

 

The appendix section of the new traffic report contains Intersection Capacity Utilization (ICU) summary sheets on page 16 and 18 showing that Graham & Warner intersection data was collected on August 29, 2002, which is BEFORE the start of the Marine View academic calendar. 

 

Since peak traffic conditions in this area are driven by Marine View, collecting any data when school is not in session will produce an undercount not representative of typical peak conditions.

2.2 Holiday Week Traffic Counts Atypical

 

The new traffic study counted cars on Graham Street on Wednesday September 4th and Thursday September 5th which fall in the short post-Labor Day holiday work week.  It is the traditional end of summer vacation period, with families traveling out of the area (and not driving theirs cars on Huntington Beach streets).

 

We assert that counting cars under the lighter than normal traffic conditions of the 4-day post-Labor Day work week has produced an undercount not representative of typical peak conditions.

2.3 School Enrollment Takes a Few Weeks to Ramp Up

 

According to Sharon Tugwell of OVSD Financial Services, school enrollment slowly increases during the first few weeks as clueless parents realize that school has resumed, as families return from summer vacations, and as new students transfer in from year-round districts with differing academic calendars.  Because of this variability, the district will not even bother collecting their first official enrollment statistics for 2002 until September 27th.

 

Therefore, any traffic study (such as this one) that measures traffic on the first two days of school will likely produce an undercount not representative of typical peak conditions.


2.4 HCM Summary Sheet Intersection Delay Times Suspect

 

The HCM summary sheets in the appendix contain delay times for the Graham & Glenstone intersection.  However, due to the impaired sightlines from where the human traffic counters were parked on the south side of the Wintersburg bridge, it would have been impossible to see the trailing, northernmost edge of the queue of Graham cars waiting to turn left onto Glenstone.  If you cannot see the end of the queue, you cannot accurately measure the queue delay time.

 

The arrow in the following photograph indicates the position where the human traffic counters were dangerously and illegally parked in the bike lane in a no-parking zone on the Wintersburg bridge:

 

 

 

Because the parking location was on the down slope of the bridge, the top of the bridge impedes the sightlines that would be required to see the end of the left turn queue. 

 


The following photograph shows what a driver parked in the above location would see when looking in the rear view mirror:

 

 

Note that the above photograph is of a reflection in the driver’s rear view mirror of the author’s Camry, and so Kenilworth is on the right hand side out of sight below the crest of the bridge.  We also cannot see the point on Graham between the top of the bridge and Kenilworth where the end of the Glenstone left turn queue forms.  If you cannot see the end of this queue, you cannot properly compute the intersection delay times.

2.5 Unrealistic Benefits from Restriping

 

Comparing HCM summary sheet pages 36 and 40 shows that the applicant believes their Graham restriping “mitigation” will reduce the Marine View drop-off delay from 29.45 seconds (likely too low – see item 2.4 above) down to 13.46 seconds.  This is an absolutely fraudulent claim, because Marine View drop-off drivers are already driving in the same imaginary left turn median that the applicant proposes to paint on the road.  Since restriping would simply mirror existing behavior, there will be no major change in intersection delay time.

2.6 Summary

 

The September 2002 traffic study confirms that existing traffic is indeed worse than depicted in the July 2002 Final EIR.  It is worth noting to compare the Graham & Glenstone AM peak HCM summary sheets for the 1997 and 2002 “existing plus project” cumulative conditions (pages 28 and 36).  We see that southbound Graham turning left onto Glenstone has degraded from LOS B down to LOS D. 

 

Since LOS D is considered to be the minimum acceptable Level of Service, it is important to redo the traffic study in a manner safe from accusations of undercounting.  Perhaps an accurate count will show the true condition to be LOS E (i.e. unacceptable).

 

3. A Rebuttal to Dick Harlow Regarding Graham & Neargate

 

The applicant’s lobbyist, Dick Harlow, conveniently gave the last public comment on September 10th without any opportunity for rebuttal.  Harlow asserted that since the Neargate tract west of Graham and south of Slater doesn’t experience any traffic-related problems with their single entrance/exit, then the similar-sized Parkside project won’t experience (or cause) any traffic problems either with their single entrance/exit at “A” street.

 

This laughable statement is basically comparing apples to orangutans, completely ignoring the fact that these two intersection environments are totally different.

 

First, the 2002 edition of Thomas Bros. Maps shows the Parkside segment of Graham to be arterial, whereas the Neargate segment is non-arterial:

 

Text Box: Non-arterialText Box: Arterial

 


Second, Graham dead-ends south of Neargate.  The only traffic on this segment of Graham is from Neargate or Ridgebury residents; there is no through traffic:

 

Not a

through

street

 

 

Third, the Graham traffic volumes and congestion are much, much higher at “A” street that at Neargate.  The following photograph shows what southbound Graham morning peak traffic looks like at “A” street:

 

 

4. Implications of the Coastal Commission/Rivertech Letters

 

The September 10th Rivertech letter on water quality is interesting (and be sure to reread the September 9th Coastal Commission letter that prompted the Rivertech letter).  Basically it confirms the Coastal Commission's assertion that the CDS technology specified in the 1998 report (EIR Volume IIA) is nowhere near the claimed 90% efficiency rating.  The letter then refers to the 2002 water quality addendum (also EIR Volume IIA), saying they promise to do future specified BMPs (Best Management Practices), and come up with an as yet unwritten Urban Runoff Management Plan prior to issuance of the grading permit.

What we have here is confirmation of the "leading edge vs. bleeding edge" scenario contained in my long PowerPoint presentation (see http://www.bixby.org/parkside/multimedia.html).  CDS was leading edge in 1998, but had a very skimpy track record with only 9 installations in the USA.  And what do you know, with the passage of time a track record developed for CDS that seriously failed to live up to the manufacturer's hype.  Thus instead of "the leading edge", we find ourselves at "the bleeding edge".

Shea/Rivertech (and likely Public Works too) became aware of this problem, and wrote the 2002 water quality addendum that appears in EIR Volume IIA (http://www.bixby.org/parkside/documents/EIR/VolumeIIA/5/2002.pdf).  However, this little document only talks about adding extra BMPs and promising to create an URMP in order to meet standards.  NOTE THAT THERE IS NO DISCUSSION ABOUT THE FAILINGS OF THE CDS TECHNOLOGY IN THIS SECTION OF THE EIR.  This little tidbit would have remained hidden were it not for the Coastal Commission's September 9th letter.  I guess you could say the EIR is covering up the CDS unit's problems.  If I was a planning commissioner, I might be a little peeved about that!

All sides agree that CDS is not sufficient.  Hence the creation of the "treatment train" described in the 2002 addendum.  And if you read the very last paragraph of the September 10th Rivertech letter, it says they are "currently investigating the use of sand filters for treating urban runoff".  So they're not even finished yet specifying the structural BMPs!  Not to mention that future URMP that hasn't even been written yet.

How is it even possible that a project like Parkside -- which hasn't finished its structural water quality design and hasn't finished creating its management plan for dealing with urban runoff -- is up for approval?  If the Planning Commission approves this project on September 24th, it will be really only approving on the basis of vague water quality promises.  What has been completed at this point in time will not meet water quality standards.

Beware of promises from applicants who omit bad news from EIRs.  The City should use its maximum leverage that only exists in the pre-approve/deny stage to get the applicant to really and truly commit to what their plans are going to be for ensuring that our local water quality isn't harmed by this project.


5. Subsidence - Up Close and Personal

 

Homes on Kenilworth suffer from serious subsidence problems, both historical and ongoing.  The damage is most serious in the area where the sinuous dark channel-type pattern (running parallel to the Wintersburg Channel) on the Shea property intersects Kenilworth:

 

 

Patios are cracking:

 

 

Walls are separating:

 

 

The southern boundary wall is sinking:

 

 


Extensive rework is needed to restore the original height and level surface (note that 12 inches were added to restore the original wall height):

 

 

Kenilworth residents have serious concerns about the potential negative impacts from both the project’s extensive dewatering plan and the subsequent importation of approximately 5 feet of fill onto the site.  Who will be liable for damages if this project worsens known subsidence problems?


6. Ponding Demonstrates Wetlands Status

 

We have an extensive photographic archive showing the multiple consecutive days of ponding required to demonstrate that this land is indeed a wetlands:

 

 

We also have photographs showing active grading being done to fill in the pond areas:

 

 

Yet despite the best efforts of the applicant, the land reasserts its true wetlands nature, resulting in a tractor becoming stuck for several weeks in a large lake:

 

 

The best 164 of these images are available on a companion CDROM labeled “Shea Ponding Vol. I”.  Filenames use YYMMDD date-based prefixes to tell you when each photograph was taken.  This free CDROM is available upon request from the author.  Planning Commissioners should have received a copy in their Planning Commission agenda packets.

 

7. EIR Deficiencies

 

We believe the July 2002 Final EIR is fatally deficient as currently written and should not be certified.

7.1 Traffic

7.1.1 Graham Restriping as a Fraudulent Mitigation

 

The EIR proposes restriping Graham Street between Warner and Slater with a left turn median in order to mitigate the traffic increase caused by this project.  We find this to be a fraudulent mitigation because today’s Graham drivers already use this entire segment of Graham as a de-facto left turn median.  Painting some new stripes on the road merely recognizes existing driver behavior and will not reduce the extra congestion caused by this project, particularly at Glenstone.

 

A genuine mitigation that would truly help Graham would be to install a signal at the intersection with Glenstone.  However, the EIR does not consider this option.


7.1.2 Kenilworth Left Turn Impact Omitted

 

The EIR asserts that adding a signal at the project’s “A” street intersection with Graham will have no negative impact on traffic circulation.  This patently absurd statement ignores the extreme length of the southbound Graham queue waiting to turn left at Glenstone.  Adding a signal at “A” street will guarantee that this queue extends northward from the new signal so that it will block cars trying to exit from Kenilworth to turn left onto Graham.

 

This impact is not acknowledged in the EIR, nor are any mitigations offered.

7.1.3 September 9th 2002 Traffic Study Flawed

 

The updated traffic study contains numerous flaws that invite charges of undercounting.  The loyal opposition thanks you for giving us so many easy things to challenge.

7.2 Drainage/Hydrology

 

The EIR assumes that no County permit will be needed to install the additional pumps at the Slater Pump Station, but dedicated work by the loyal opposition has prompted the County to say that a permit WILL BE REQUIRED.  The EIR does not consider the impacts of any conditions the County will impose on this permit, including but not limited to stilling well throttle-back sensors or on-site detention facilities.  Some of these possible conditions have the potential to invalidate the current FEMA CLOMR, which in turn could alter the amount of fill required for this project to meet flood insurance regulations.

 

The applicant has agreed that seeking a County permit is acceptable, and we ask that this be REQUIRED as a condition of this project.  Due to the potential significant impacts involved in seeking such a permit, a dialog must be started with the County and additional analysis performed before this EIR can be certified.

7.3 Water Quality

 

The EIR does not analyze the negative water quality impacts resulting from the increased pumping of the Slater Pump Station that will occur due to the project’s runoff being dumped into the Slater Channel.  The Slater Channel is highly polluted and this project will cause that pollution to enter the Wintersburg Channel more frequently, eventually flowing down into Bolsa Chica and Huntington Harbour.  Please see my attached letter dated September 13th, 2002, that I sent to the Coastal Commission regarding this issue.

 

As the September 10th Coastal Commission letter points out, the water quality impact of this project upon Bolsa Chica and Huntington Harbour is not addressed.

 

Furthermore, the EIR does not analyze moving the 2 new storm pumps to the northern side of the Wintersburg Channel as an alternative drainage method that would directly connect to the Wintersburg without first passing through the polluted Slater Channel, thus yielding superior water quality.

 

There is a passage hidden in EIR Volume IIA in the 1998 water quality report on page 4-1 that reads:

 

“Although the storm drain system is designed to accommodate the flow during the 100-year storm event, it has certain deficiencies during non-storm periods. Water elevation in the Slater Channel during non-storm periods is frequently higher than the invert elevations of the storm drains at Nodes 250,211 and 608. The flap gate at node 609 is provided to minimize the reverse flow from the Slater Channel to the storm drain system during non-storm periods. Even if the flap gate is fully leak proof, dry weather flow from on-site and off-site areas is expected to accumulate within the storm drain system. This may create anaerobic conditions and produce odor problems within the development. Further, during early stages of a storm when this severely degraded dry weather flow finds its way to the Slater Channel it will adversely impact the quality of water in the downstream channels.”

 

The water quality impacts and the odors discussed above conveniently do not appear within the main impact sections of the EIR, and neither are any mitigations offered.

 

The water quality section of the EIR is ultimately based on vague promises to do future work in order to meet standards.  Vague promises of future planning should not be a substitute for completed planning in the early stages that can be evaluated during the approval process.

7.4 Noise

 

The EIR discloses the various noise impacts resulting from the construction process, but does not analyze the CNEL noise impact of the haul route scenario that uses Graham if the borrow site is not adjacent.  This is a glaring deficiency in and of itself and is made worse by the fact that the September 2002 traffic study shows substantially more cars on Graham today.  Sound impacts are cumulative, and the impact of added haul truck traffic on top of today’s busier Graham traffic simply hasn’t been analyzed.

 

Additionally, the project site is located directly under the landing flight path for Long Beach Municipal Airport and/or Los Alamitos Armed Forces Reserve Center.  There is a daily mix of various jet types flying overhead, ranging from smaller executive jets to commercial air cargo carriers (i.e. FedEx, etc) to gray, lumbering military behemoths.  The commercial air cargo jets fly low enough to make out the corporate logo on the aircraft’s tail.  CNEL was designed to measure airport noise impacts, but curiously the EIR omits all mention of airport noise for both the existing and developed conditions.


7.5 Public Safety

 

Given that the Fire Department is only confident (but not certain) that Edwards Station will be capable of meeting response time criteria (within 5 minutes 80% of the time) for the area, we feel that the EIR does not adequately address the impacts to existing residents of amending the General Plan to remove the current fire station designation from the applicant’s property. 

 

The EIR also didn’t consider a development alternative incorporating a fire station within the project boundaries.

 

Loyal opposition driving tests to the southernmost existing homes in this area strongly suggest that the Fire Department’s confidence of meeting the 5-minute response time standard is rather dubious, with actual response times more likely to be as much as 6 minutes for both Edwards Station and the proposed relocated Heil Station. 

 

As of this writing (09/19/02), the Fire Department has NOT provided any rebuttal to these unofficial driving tests, either in the form of actual dispatch times or official driving tests all of the way to homes at the southern boundary of the area (rather than just to the intersection of Graham & Slater).

7.6 Egregious Typographical Errors

 

EIR Volume II Section 5.10 page 5-175 asserts that Marine View Middle School is “approximately four (4) miles from the [project] site”, when in fact the distance is only 0.4 (four-tenths) miles.  If this egregiously erroneous distance of 4 miles was used in any subsequent calculations or analyses, the conclusions are also erroneous.

 

8. Requested Changes in Project Conditions

 

We believe the EIR is deficient and should not be certified.  However, if the Planning Commission goes ahead and certifies the EIR anyway, we would like to see the following conditions added to the project:

8.1 Traffic

 

  • We request that a condition be added to implement Circulation Alternative B in order to provide a second tract entrance/exit to Bolsa Chica Street that will reduce the project’s impact on Graham Street.

 

  • We request that a condition be added to fund the installation of a signal at the intersection of Graham & Glenstone to be completed by the time the occupancy permits are issued for the project.

 

  • We request that a condition be added to add “Keep Intersection Clear” striping and signage to the intersection of Graham and Kenilworth.

 

  • We request that a condition be added to forbid the use of stop signs for controlling through traffic on “B” street in order to prevent stop & go traffic noise from impacting existing residents on the south side of Kenilworth.

 

  • We request that the condition allowing the connection to Greenleaf to be opened to non-emergency access be contingent upon a City Council public hearing AND a simple majority vote by residents living in the tract north of the project site.

8.2 Drainage/Hydrology

 

  • We request that a condition be added to REQUIRE seeking a County permit for installation of the 2 new storm pumps being proposed for this project.

 

  • We request that a condition be added to establish an “Improvement District” comprised of all parcels within the Parkside project to provide “all funding whatsoever” for the operation, repair, replacement, inspection, licensing and/or maintenance in perpetuity for an Urban Runoff Pump Station (which will pump directly into the Wintersburg Channel) to be located on or about Lot “O” as shown on the current Conditional Land Use Plan.

    All operations whatsoever concerning the new pump station are to be carried out under license and supervision of the City of Huntington Beach with all costs whatsoever to be borne by the new Improvement District.

    The benefits of this alternative are many and obvious:

 

    • Dick Harlow has stated that such a configuration will cost the applicant less money to build.

 

    • A direct connection to the Wintersburg Channel offers superior water quality because the badly polluted Slater Channel will not experience increased pumping as a result of this project.

 

    • Handling significant new runoff with a new, independent pump station offers better public safety because the Slater Pump Station will no longer be a single point of failure.

8.3 Water Quality

 

  • We request that this project not be approved until the applicant commits in writing their complete selection of all structural BMPs and the associated URMP.  Water quality is far too important to proceed on vague promises by a group of people whose initial plans were proven insufficient.

8.4 Public Safety

 

  • We request that a condition be added to require the funding and construction of a fire station on the project site as per the original General Plan zoning designation if the Fire Department cannot be certain that Edwards Station and relocated Heil Station will meet the city response time criteria for all existing homes in the area and the applicant’s new homes.

 

 

Sincerely,

 

 

 

Mark D. Bixby

Neighbors for Wintersburg Wetlands Restoration

17451 Hillgate Ln

Huntington Beach, CA  92649-4707

714-625-0876

 

attachment