Notes
Slide Show
Outline
1
Neighbors for Wintersburg Wetlands Restoration
2
The NWWR Vision
  • Acquisition and Re-integration with the Greater Bolsa Chica Ecosystem
  • Restoration of the wetlands, functioning as a Natural Treatment System, Flood Buffer, and Wildlife Habitat
  • Filtration of urban runoff that would otherwise flow into Huntington Harbour
3
IRWD Treatment Wetlands
  • Type I -- Offline
  • Type II -- Inline
  • Type III -- Co-located  Within Detention Basins
4
The Shea Parkside Vision:
Ill-Conceived and Poorly Planned
  • Loss of wetlands
  • Increased traffic problems
  • Increased flood threat
  • Increased water pollution
  • Threat of home damage by subsidence
  • Fire response deficiencies
  • Numerous other concerns


5
It’s Really a Wetlands!
  • Three parameters for wetlands delineation:


  •  Hydric soils
  •  Hydrophytic vegetation
  •  Consecutive days of ponding water


  • This property exhibits all three.  The Coastal Commission only requires just one!
6
Coastal Commission July 3, 2001 letter
  • “Though the area may have contained wetlands in the late 1980’s, the DFG (March 16, 1998) concurred with a wetland evaluation …that the 44 acre City Parcel did not currently meet wetland criteria.”
7
Where’s the 100-foot setback?
  • Coastal Commission July 3, 2001 letter notes the potential for wetlands to exist in the County portion, and mentions the need for a 100- to 300-foot setback buffer
  • May 21, 2002 LSA wetlands delineation study finds potential Commission wetlands in County portion, yet no setback is included in the tract map
8
100-foot setbacks on the County parcel
9
Hydric Soils
May 21 2002 LSA report in EIR
  • Documents hydric soils on County portion, but speculatively dismisses the findings:
    • “may be remnants from a time prior to construction of the Wintersburg Channel”
    • “soils exhibiting hydric indicators were deposited on site, and were then intermixed with the native soil during past ground disturbance activities” (i.e. illegal dumping)
  • These assertions cannot be proven!
  • Ignores the likelihood these hydric soils result from current wetlands conditions
10
Hydrophytic Vegetation
  • LSA uses the illegal dumping excuse to dismiss the presence of hydrophytic vegetation on the County portion (cannot be proven!)
  • EIR responses to comments dismiss hydrophytic vegetation by blaming it on seeds laying dormant for years and then suddenly sprouting in unusually wet years (DUH!!!)
11
Consecutive Days of Ponding Water
  • See Dr. Jan Vandersloot’s
    June 14, 1998 comment letter in EIR Volume III
12
16+ Consecutive Days of Ponding
  • December 7, 1997 – December 22, 1997
13
 
14
 
15
 
16
 
17
 
18
 
19
 
20
 
21
 
22
 
23
 
24
 
25
45 Consecutive Days of Ponding
  • January 12, 1998 – February 26, 1998


26
 
27
 
28
 
29
 
30
 
31
 
32
 
33
 
34
 
35
Plus additional omitted photographs taken on the 10 days of
January 22-31, 1998
36
 
37
 
38
 
39
 
40
 
41
 
42
 
43
 
44
 
45
 
46
 
47
 
48
 
49
A River Runs Through It
  • (and so does illegal dumping of fill)
50
Things to look for
  • The “ephemeral” channel running through the site, consistently visible over 30 years (only briefly mentioned by EIR)
  • Substantial illegal fill dirt being dumped in the Smoky’s Stables area in order to raise land elevations
  • Correlation to daily rainfall records show consecutive days of ponding in many years (and not just El Nino years!)
    • 8.3ac former EPA-designated wetland
    • Additional ponds adjacent to the Wintersburg
51
12/26/52 - EIR
52
3/24/59 – EIR – ponding 36+ days – way below avg season
53
 
54
 
55
6/28/70 - EIR
56
10/26/73 - EIR
57
2/17/75 - EIR
58
12/28/76 - EIR
59
 
60
12/14/78 – EIR – ponding 31+ days – above avg season
61
 
62
1/31/81 – EIR – ponding 4+ days – below avg season
63
 
64
 
65
 
66
 
67
 
68
 
69
3/19/86 – EIR – ponding 11+ days – avg season
70
 
71
 
72
 
73
 
74
 
75
 
76
 
77
 
78
 
79
 
80
 
81
 
82
 
83
1/24/92 – EIR – rain 1/3/92 – avg season
84
 
85
1/3/93 – EIR – rain 12/28/92 – way above avg season
86
 
87
5/14/93 – EIR – rain 3/26/93 – way above avg season
88
1/3/94 – EIR – rain 12/12/93 – below avg season
89
 
90
 
91
 
92
3/27/95 – EIR – ponding 22+ days – way above avg season
93
 
94
 
95
 
96
 
97
Total precipitation (inches) for seasons with 18 or more consecutive days of ponding
98
But Shea had a problem -- too much proof of ponding!
  • Solution: Fill in the ponding areas!
99
 
100
 
101
 
102
 
103
 
104
 
105
But the ponding still persisted…
106
March 14, 2001
107
March 18, 2001
108
March 23, 2001
109
The solution to incriminating ponding?
  • More “farming” with bulldozers!
110
March 28, 2001
111
Selective Soil/Water Testing
  • Avoided the “interesting” locations
112
Need Soil Tests in Subsidence Zone
113
Insufficient Testing for PCBs in Soil
  • “No transformers” assumed to mean no PCBs
  • There has been no soil testing to date to check for PCBs
  • This seems grossly irresponsible given the proximity to the confirmed PCB dumping ground at the end of Graham Street
  • CA DTSC has been contacted…
114
Water test pit locations – March 1997
115
Tidally-influenced groundwater
116
LSA Report Inaccurate Regarding “prior converted croplands”
  • EIR erroneously states that in 1992 Army Corps said that there were no wetlands
  • Army Corps really just said that they could not exercise jurisdiction
  • “Prior converted croplands” designation is irrelevant to the Coastal Commission, which uses a different set of definitions
117
Prior Converted Croplands or Farmed Wetlands?
  • Prior Converted Cropland – inundation less than 15 consecutive days
  • Farmed Wetlands – inundation for 15 or more consecutive days (subject to CWA Section 404 regulations) in at least 51% of rain seasons
  • Our current photographic database can prove Farmed Wetlands status in 44% of seasons since 1966-1967
118
A New Wetlands Delineation is Overdue for the City Parcel
  • Delineations are only valid for 5 years, and the last one is getting old:
    • 11/23/96 first site visit (nearly 6 years ago)
    • 07/11/97 amended final draft (over 5 years ago)
    • 11/20/97 last site visit (4 years 11 months ago)
    • 12/17/97 Lisa Kegarice delineation letter sent
      (4 years 10 months ago)
119
New Delineation Justified by Sloppy Work and New Evidence
  • Coastal Commission has not said they agree with the old delineation
  • Sloppy water table testing the first time
  • New aerial ponding evidence
120
Kegarice used the WRONG delineation manual in 1997!
  • 1987 USACE delineation manual was used
  • Hydric soil info was obsoleted in 1992
  • 1994 Memorandum of Understanding said that the National Food Safety Act Manual (NFSAM) will be used for federal delineations of agricultural land
  • NFSAM updated in 1996 with “Field Indicators of Hydric Soils”
  • A new delineation must be performed using NFSAM!
121
Buried Secrets – July 13, 2001
  • Or, Indiana Jones and the Storm Drain of Doom
122
The map shows the existing
 60” storm drain
123
Shea contractors dug several deep holes near the storm drain
124
Bricks & quick-set mortar were installed down in the holes
125
Public Works denies all knowledge
  • HB DPW initially said it is a County drain
  • County said it is a City drain
  • HB DPW then agreed it is a City drain, but had no idea of what work was being done
  • HB DPW then surmised that Shea was merely confirming the location of the drain


  • But later that night, the truth is discovered!
126
Indiana Jones and
The Storm Drain of Doom
  • A member of the loyal opposition enters the storm drain after midnight to explore
  • Apparently there are multiple southerly extensions (leach lines) of this drain running under the Shea property
  • The Shea contractors had bricked off these extensions in order to prevent water from the main drain from flowing under the Shea property
127
The map neglects to mention the leach lines that are now sealed
128
What was Shea up to here?
  • De-watering a wetland whose status is still subject to legitimate debate?
  • Performing work on city storm drains without a permit?
  • Increasing the load on the already overburdened Graham storm drain?
  • Unethical behavior that should not be implicitly sanctioned by the City of HB?
129
Wetlands Summary
  • Proven ponding tendencies (not just El Nino years)
  • Repeated, unpermitted actions by Shea to prevent future ponding
  • Sloppy, improper, no longer valid wetlands delineation of the city parcel
  • EIR should not be certified without a new wetlands delineation for the city parcel
130
Water Quality Issues
131
Hidden Negative Water Quality Impacts
  • Parkside adds significant new runoff to the Slater Channel
  • More frequent Slater pumping will be needed to maintain the -6 ft MSL elevation
  • Slater pollution will enter the Wintersburg Channel more frequently than today
  • Resulting in extra days of pollution for Bolsa Chica & Huntington Harbour
132
Solution: Move the New Pumps to the North Bank of the Wintersburg
  • WIN – costs less to build
  • WIN – doesn’t send extra Slater pollution to Huntington Harbour
  • WIN – superior safety by not relying on Slater Pump Station as a single point of failure
  • WIN – all maintenance expenses whatsoever could be funded via Improvement District
133
What’s that awful smell???
134
September 20th Coastal Commission letter on water quality
  • “fundamentally flawed”
  • “used inaccurate data and assumptions”
  • “there will not be 45% area-wide reductions”
  • “impacts to Huntington Harbour…have not been fully considered”
  • “impacts to the Bolsa Chica Reserve have [not] been fully considered”
135
Water Pollutant TMDLs are Coming for Huntington Harbour
  • 303(d) pollutant limits will be established in the 2006-2010 timeframe, according to the Santa Ana RWQCB
  • Adding Parkside pollution today will make it harder and more expensive to meet these limits tomorrow
  • HB will be stuck paying the clean-up bill, not Shea!
136
Drainage/Hydrology Issues
137
City/County Disagreement on Slater Pump Station permits
  • Bob Righetti and other city staff insists no permits are needed for the new Shea pumps
  • But the County insists that permits are REQUIRED!
    • 05/27/98 County letter DEIR comment
    • 09/04/02 County letter to Public Works
  • City still denies the permits are required


138
Lack of Cooperation
  • City insists the original 1964 Slater Pump Station permit covers new Shea pumps
  • Though conditions have changed greatly in the past 4 decades, no new permit will be sought from the County
  • The County has ultimate authority over the Wintersburg, a key piece of public safety infrastructure which doesn’t meet modern design standards, and should be consulted
139
Evading the Safety Limits?
  • County required an automated stilling well throttle-back sensor for the Shields Pump Station to protect the Wintersburg
  • No County permit and no such sensor is planned for the Slater Pump Station
  • The Slater Pump Station should be held to the same modern safety standards as the Shields Pump Station!


140
Increased Flood Threat:
Another Deficient EIR Analysis
  • Parkside adds to runoff in Slater Channel, so the pump station will be expanded…
  • …but the County may require throttle-back limits to protect the Wintersburg Channel from overflowing
  • Therefore if the Wintersburg is full, the new Slater pumps may not operate, thus increasing the risk of a Slater Channel flood which is not analyzed by the EIR
141
A Questionable FEMA CLOMR
142
Don’t be fooled!
143
Shifting the Flood Risk
  • Parkside runoff north of the Wintersburg will be sent south to the Slater Channel
  • Existing Slater neighborhoods will be at risk during El Nino-class storms at Wintersburg high tide
  • Shifting the risk burden to other neighborhoods is bad public policy, and so are single point of failure designs!


144
EIR Deficiency:  Does Not Analyze Any Drainage Alternatives
  • No discussion of the MUCH simpler solution of building a new pump station at Lot O and directly connecting to the Wintersburg Channel
  • All costs whatsoever could be funded by an Improvement District
145
EIR Deficiency:  Does Not Analyze Impact to Local Aquifers
  • Seawater intrusion already a problem
  • Paving this property will greatly reduce aquifer recharge from fresh rainwater
  • Seawater intrusion will then worsen
  • Orange County aquifers currently significantly overdrawn due to drought and population increase
146
EIR Deficiency:  No Analysis of Impacts of Drainage Failures On  Kenilworth Tract
  • Parkside will sit at significantly higher elevation than adjacent Kenilworth tract
  • If there is failure of any component of the Parkside drainage system (i.e. clogged drains, etc), flood conditions will compound for the Kenilworth homes and surroundings
  • EIR does not analyze or mitigate for these failure conditions
147
Subsidence Issues
148
Kenilworth Subsidence Zone
149
Patios are cracking
150
Walls are splitting
151
Walls are tilting
152
Walls are sinking…
153
…by as much as 12 inches!
154
Insufficient Protections During Overexcavation & Dewatering
  • Shea insists these techniques are time-tested and won’t harm adjacent homes
  • HB has history of residential subsidence problems
  • Shea promises careful monitoring, but the first signs of trouble may be cracked foundations on Kenilworth homes
  • Shea and/or HB will be held liable for any problems during construction or thereafter
  • If they’re so certain of their mitigation measures  they should provide indemnification for any and all casualty loss to existing homeowners
155
Liquefaction Issues
156
Liquefaction:  New Threat Caused by Mitigation in Final EIR
  • Liquefaction can occur on any wet, uncompacted sub-strata during a temblor
  • Parkside plans propose a 50’-wide Paseo Park to mitigate vibration and likely subsidence problems
    • sloped toward 22 existing homes on Kenilworth
    • they claim that ‘neither dewatering nor remedial grading will be required…’
    • made of tens of thousands of cubic yards of fill
157
Liquefaction:  New Threat Caused by Mitigation in Final EIR
  • The wet, uncompacted sub-strata together with the new fill would be subject to liquefaction, therefore the whole slope would be at extreme risk for liquefaction and slumping during a temblor, endangering homes on Kenilworth
  • The Final EIR doesn’t account for this newly created and foreseeable problem which is a likely consequence of their proposed mitigation


158
Traffic Issues
159
We Demand a Traffic Study Recount!
  • Data collected during Labor Day week when many people are away on summer vacations (and not driving on HB roads!)
    • OVSD gym EIR says collecting traffic data during “typical weekday peak commute hours” is best (this EIR was the result of a successful court challenge)
    • Holiday weeks are not “typical”!
  • OVSD enrollment was still ramping up
160
OVSD Enrollment Still Ramping Up
  • Some families still on vacation
  • Clueless parents slow to realize school has resumed
  • Incoming transfers from year-round districts with different academic calendars
  • First enrollment statistics not collected until September 27th
161
1997+Project HCM p.28
Southbound Graham at Glenstone
162
2002+Project HCM p.36
Southbound Graham at Glenstone
163
Restriping – a Fraudulent Mitigation
  • The EIR proposes left-turn median striping to mitigate Graham congestion
  • But drivers are already using a de-facto left-turn median of their own creation
  • So painting some extra lines in the middle of Graham won’t change anything!
  • How about conditioning for a traffic signal at Graham & Glenstone instead?
164
Restriping still a bogus mitigation!
2002+Project+Improv HCM p.40
165
Increased Traffic Congestion
  • Graham Street already congested at peak periods
  • Congestion will be worsened by:
    • Marine View gym (in progress)
    • Parkside (proposed)
    • Hearthside/Fieldstone (proposed)
  • “Circulation Alternative B” (exit to Bolsa Chica St) needed to reduce the additional burden on Graham Street!
166
Pressure to open Greenleaf to through traffic
  • Connection to Greenleaf proposed as “emergency only” access
  • But a future City Council could open it up to through traffic, despite 100% Greenleaf opposition
  • Circulation Alternative B (Bolsa Chica St) would remove the Greenleaf temptation and provide suitable emergency access
167
Graham Haul Route Needs Reanalysis
  • September 9th 2002 traffic study shows significantly more traffic on Graham
  • EIR conclusions about haul route impacts are based on stale 1996 traffic data
  • These impacts of moving up to 285,000 cubic yards of fill need to be reanalyzed
168
Graham & Glenstone Peak Traffic
Thursday, February 14, 2002, 7:35AM
169
Glenstone U-turns
Friday, September 6, 2002 – 7:33AM
170
Left Turn Trouble at Kenilworth
  • Backups caused by the Parkside signal will create left turn delays when exiting Kenilworth onto northbound Graham
  • Southbound cars waiting at the signal will cause dangerous visibility problems
  • “Keep Intersection Clear” striping won’t solve the visibility problem
171
North Graham from Kenilworth
Monday, September 9, 2002 – 7:31AM
172
South Graham from Kenilworth
Monday, September 9, 2002 – 7:31AM
173
Fire/Medical Response Issues
174
Planning Commission Decision:
Certify the Parkside EIR
Based Upon CEQA Compliance
  • Analyzes the potential environmental impacts
  • Identifies project alternatives
  • Identifies mitigation measures to lessen the project’s impacts
175
“Analyzes the potential environmental impacts” (EIR Errata)
  • “Future development of the project site may create a need for additional fire protection services. The increase in the number of residential units and the number of individuals brought into the area, as well as the resulting increase in traffic will directly affect the fire department's responses.”
  • “Additional impacts to current response times are anticipated with relocation of the [Heil] fire station.  Response time from the new location to the project site would be greater than 5 minutes.”
  • “Implementation of Mitigation Measure 1 will reduce impacts related to the need for adequate response times and additional fire protection services to a level less than significant.”
176
Edwards Response Time Estimates
177
“Identifies project alternatives”
  • No project/no development
  • Development under existing zoning
  • Alternative location
  • Alternative park site location
  • Alternative roadway connections
  • Reduced density alternatives (4)


  • Development incorporating the existing General Plan fire station designation is NOT included in EIR!
178
Keep the General Plan
Fire Station Designation!
  • HB General Plan clearly shows the Graham/Slater area to be emergency response deficient.
  • Recent H.B.F.D. tests have not proved otherwise; so much for “exceptional degree of overlapping coverage” from Warner, Edwards, and “Relocated” Heil stations.
  • G.P. Policy P.F. 2.1.1 “Locate fire stations in a manner which will enable fire response times to meet a five minute standard, 80% of the time.”
  • Graham/Slater residents are just as entitled to prompt emergency service as other residents!
179
Types of Calls to H.B.F.D.
(by percentage)
180
Parkside EIR fails on All 3 Counts:
  • It does NOT adequately analyze the potential Public Services environmental impacts to surrounding homes.
  • It does NOT identify a project alternative incorporating a fire station.
  • It does NOT identify mitigation measures to lessen the project’s Response Time impacts to surrounding homes, nor does it identify any medical safety mitigations.
181
Aesthetics/Light and Glare Issues
182
Headlight Mitigation Too Slow
  • Car headlights on project streets will shine into Kenilworth homes
  • Paseo Park will be landscaped to block this light
  • But these trees won’t be planted until construction is completed in 4 years
  • The trees won’t reach mature headlight-blocking heights for another 5 years
183
Noise Issues
184
Graham Street Haul Route Impact Needs Reevaluation
  • September 9th traffic study shows substantially more existing traffic (and thus noise) on Graham
  • If the adjacent Bolsa Chica mesa cannot be used for the fill borrow site, Graham will be used as the haul route
  • EIR needs to reevaluate Graham haul route noise impacts in light of higher traffic levels
185
Construction Schedule Will Impact Retirees and Telecommuters
  • City construction schedule is Monday – Saturday, 7AM – 8PM
  • Impacts to retirees, telecommuters, and swing shift workers, stay-at-home moms, children and care-givers are not discussed
  • The proposed mitigation measures will not reduce the impacts for these classes of residents
186
Aircraft Noise Impacts Omitted
  • Neighborhood is under the Long Beach / Los Alamitos landing flight paths
  • Military and commercial aircraft fly low enough to read tail logos
  • Beach banner aircraft also present during summer months
  • EIR does not factor any of this aircraft noise into its CNEL impact calculations
187
On Final Approach to Long Beach
188
Suggested Conditions of Approval to Reduce the Negative Impacts
189
Suggested Conditions of Approval
Traffic
  • Require a secondary entrance/exit
  • Require signalization of Graham & Glenstone
  • Forbid the use of stop signs on “B” street to reduce noise impacts to adjacent Kenilworth homes
  • Hold Shea to their repeated promises to convey property rights to Kenilworth / Greenleaf homeowners to give them control of access, preventing opening of Greenleaf Lane to through traffic.
190
Suggested Conditions of Approval
Drainage/Hydrology Conditions
  • Seeking a County permit for new storm pumps must be REQUIRED (the current phrase “necessary permits” leaves too much wiggle room)
  • Install the new pumps at Lot O for direct connect to the Wintersburg Channel, with all costs whatsoever funded by an Improvement District
191
Process Issues
192
Accuracy Counts!
  • Invalid maps at study sessions
  • Missing sections from Final EIR
  • Contradictory statements remain in Final EIR
  • Egregious typos (“4 miles to Marine View”)
  • Half-baked fire response testing
  • Stale, fantasy traffic data
  • Botched staff report distribution
  • Staff in denial regarding County permit requirements for Slater Pump Station
193
But wait, there’s more…
  • Frequent release of significant new information as “Late Communications”
  • Bob Righetti of HB DPW refusing to return e-mails and voice mails
  • Dean Albright’s traffic maps withheld from agenda packet by Scott Hess
194
Conclusions
195
It’s Simply a Bad Project
with a Bad EIR!
  • It’s a fundamentally unbuildable wetland
  • Too many negative impacts on existing neighborhoods; Existing homeowners need better protection and indemnification against damage/loss
  • Too many omitted impacts and non-mitigations in the contradictory, error-laden, deficient Final EIR
  • Fails to fulfill 7 of 10 City Goals stated in 1996 GP