|
1
|
|
|
2
|
- Acquisition and Re-integration with the Greater Bolsa Chica Ecosystem
- Restoration of the wetlands, functioning as a Natural Treatment System,
Flood Buffer, and Wildlife Habitat
- Filtration of urban runoff that would otherwise flow into Huntington
Harbour
|
|
3
|
- Type I -- Offline
- Type II -- Inline
- Type III -- Co-located Within
Detention Basins
|
|
4
|
- Loss of wetlands
- Increased traffic problems
- Increased flood threat
- Increased water pollution
- Threat of home damage by subsidence
- Fire response deficiencies
- Numerous other concerns
|
|
5
|
- Three parameters for wetlands delineation:
- Hydric soils
- Hydrophytic vegetation
- Consecutive days of ponding water
- This property exhibits all three.
The Coastal Commission only requires just one!
|
|
6
|
- “Though the area may have contained wetlands in the late 1980’s, the DFG
(March 16, 1998) concurred with a wetland evaluation …that the 44 acre
City Parcel did not currently meet wetland criteria.”
|
|
7
|
- Coastal Commission July 3, 2001 letter notes the potential for wetlands
to exist in the County portion, and mentions the need for a 100- to
300-foot setback buffer
- May 21, 2002 LSA wetlands delineation study finds potential Commission
wetlands in County portion, yet no setback is included in the tract map
|
|
8
|
|
|
9
|
- Documents hydric soils on County portion, but speculatively dismisses
the findings:
- “may be remnants from a time prior to construction of the Wintersburg
Channel”
- “soils exhibiting hydric indicators were deposited on site, and were
then intermixed with the native soil during past ground disturbance
activities” (i.e. illegal dumping)
- These assertions cannot be proven!
- Ignores the likelihood these hydric soils result from current wetlands
conditions
|
|
10
|
- LSA uses the illegal dumping excuse to dismiss the presence of
hydrophytic vegetation on the County portion (cannot be proven!)
- EIR responses to comments dismiss hydrophytic vegetation by blaming it
on seeds laying dormant for years and then suddenly sprouting in
unusually wet years (DUH!!!)
|
|
11
|
- See Dr. Jan Vandersloot’s
June 14, 1998 comment letter in EIR Volume III
|
|
12
|
- December 7, 1997 – December 22, 1997
|
|
13
|
|
|
14
|
|
|
15
|
|
|
16
|
|
|
17
|
|
|
18
|
|
|
19
|
|
|
20
|
|
|
21
|
|
|
22
|
|
|
23
|
|
|
24
|
|
|
25
|
- January 12, 1998 – February 26, 1998
|
|
26
|
|
|
27
|
|
|
28
|
|
|
29
|
|
|
30
|
|
|
31
|
|
|
32
|
|
|
33
|
|
|
34
|
|
|
35
|
|
|
36
|
|
|
37
|
|
|
38
|
|
|
39
|
|
|
40
|
|
|
41
|
|
|
42
|
|
|
43
|
|
|
44
|
|
|
45
|
|
|
46
|
|
|
47
|
|
|
48
|
|
|
49
|
- (and so does illegal dumping of fill)
|
|
50
|
- The “ephemeral” channel running through the site, consistently visible
over 30 years (only briefly mentioned by EIR)
- Substantial illegal fill dirt being dumped in the Smoky’s Stables area
in order to raise land elevations
- Correlation to daily rainfall records show consecutive days of ponding
in many years (and not just El Nino years!)
- 8.3ac former EPA-designated wetland
- Additional ponds adjacent to the Wintersburg
|
|
51
|
|
|
52
|
|
|
53
|
|
|
54
|
|
|
55
|
|
|
56
|
|
|
57
|
|
|
58
|
|
|
59
|
|
|
60
|
|
|
61
|
|
|
62
|
|
|
63
|
|
|
64
|
|
|
65
|
|
|
66
|
|
|
67
|
|
|
68
|
|
|
69
|
|
|
70
|
|
|
71
|
|
|
72
|
|
|
73
|
|
|
74
|
|
|
75
|
|
|
76
|
|
|
77
|
|
|
78
|
|
|
79
|
|
|
80
|
|
|
81
|
|
|
82
|
|
|
83
|
|
|
84
|
|
|
85
|
|
|
86
|
|
|
87
|
|
|
88
|
|
|
89
|
|
|
90
|
|
|
91
|
|
|
92
|
|
|
93
|
|
|
94
|
|
|
95
|
|
|
96
|
|
|
97
|
|
|
98
|
- Solution: Fill in the ponding areas!
|
|
99
|
|
|
100
|
|
|
101
|
|
|
102
|
|
|
103
|
|
|
104
|
|
|
105
|
|
|
106
|
|
|
107
|
|
|
108
|
|
|
109
|
- More “farming” with bulldozers!
|
|
110
|
|
|
111
|
- Avoided the “interesting” locations
|
|
112
|
|
|
113
|
- “No transformers” assumed to mean no PCBs
- There has been no soil testing to date to check for PCBs
- This seems grossly irresponsible given the proximity to the confirmed
PCB dumping ground at the end of Graham Street
- CA DTSC has been contacted…
|
|
114
|
|
|
115
|
|
|
116
|
- EIR erroneously states that in 1992 Army Corps said that there were no
wetlands
- Army Corps really just said that they could not exercise jurisdiction
- “Prior converted croplands” designation is irrelevant to the Coastal
Commission, which uses a different set of definitions
|
|
117
|
- Prior Converted Cropland – inundation less than 15 consecutive days
- Farmed Wetlands – inundation for 15 or more consecutive days (subject to
CWA Section 404 regulations) in at least 51% of rain seasons
- Our current photographic database can prove Farmed Wetlands status in
44% of seasons since 1966-1967
|
|
118
|
- Delineations are only valid for 5 years, and the last one is getting
old:
- 11/23/96 first site visit (nearly 6 years ago)
- 07/11/97 amended final draft (over 5 years ago)
- 11/20/97 last site visit (4 years 11 months ago)
- 12/17/97 Lisa Kegarice delineation letter sent
(4 years 10 months ago)
|
|
119
|
- Coastal Commission has not said they agree with the old delineation
- Sloppy water table testing the first time
- New aerial ponding evidence
|
|
120
|
- 1987 USACE delineation manual was used
- Hydric soil info was obsoleted in 1992
- 1994 Memorandum of Understanding said that the National Food Safety Act
Manual (NFSAM) will be used for federal delineations of agricultural
land
- NFSAM updated in 1996 with “Field Indicators of Hydric Soils”
- A new delineation must be performed using NFSAM!
|
|
121
|
- Or, Indiana Jones and the Storm Drain of Doom
|
|
122
|
|
|
123
|
|
|
124
|
|
|
125
|
- HB DPW initially said it is a County drain
- County said it is a City drain
- HB DPW then agreed it is a City drain, but had no idea of what work was
being done
- HB DPW then surmised that Shea was merely confirming the location of the
drain
- But later that night, the truth is discovered!
|
|
126
|
- A member of the loyal opposition enters the storm drain after midnight
to explore
- Apparently there are multiple southerly extensions (leach lines) of this
drain running under the Shea property
- The Shea contractors had bricked off these extensions in order to
prevent water from the main drain from flowing under the Shea property
|
|
127
|
|
|
128
|
- De-watering a wetland whose status is still subject to legitimate
debate?
- Performing work on city storm drains without a permit?
- Increasing the load on the already overburdened Graham storm drain?
- Unethical behavior that should not be implicitly sanctioned by the City
of HB?
|
|
129
|
- Proven ponding tendencies (not just El Nino years)
- Repeated, unpermitted actions by Shea to prevent future ponding
- Sloppy, improper, no longer valid wetlands delineation of the city
parcel
- EIR should not be certified without a new wetlands delineation for the
city parcel
|
|
130
|
|
|
131
|
- Parkside adds significant new runoff to the Slater Channel
- More frequent Slater pumping will be needed to maintain the -6 ft MSL
elevation
- Slater pollution will enter the Wintersburg Channel more frequently than
today
- Resulting in extra days of pollution for Bolsa Chica & Huntington
Harbour
|
|
132
|
- WIN – costs less to build
- WIN – doesn’t send extra Slater pollution to Huntington Harbour
- WIN – superior safety by not relying on Slater Pump Station as a single
point of failure
- WIN – all maintenance expenses whatsoever could be funded via
Improvement District
|
|
133
|
|
|
134
|
- “fundamentally flawed”
- “used inaccurate data and assumptions”
- “there will not be 45% area-wide reductions”
- “impacts to Huntington Harbour…have not been fully considered”
- “impacts to the Bolsa Chica Reserve have [not] been fully considered”
|
|
135
|
- 303(d) pollutant limits will be established in the 2006-2010 timeframe,
according to the Santa Ana RWQCB
- Adding Parkside pollution today will make it harder and more expensive
to meet these limits tomorrow
- HB will be stuck paying the clean-up bill, not Shea!
|
|
136
|
|
|
137
|
- Bob Righetti and other city staff insists no permits are needed for the
new Shea pumps
- But the County insists that permits are REQUIRED!
- 05/27/98 County letter DEIR comment
- 09/04/02 County letter to Public Works
- City still denies the permits are required
|
|
138
|
- City insists the original 1964 Slater Pump Station permit covers new
Shea pumps
- Though conditions have changed greatly in the past 4 decades, no new
permit will be sought from the County
- The County has ultimate authority over the Wintersburg, a key piece of
public safety infrastructure which doesn’t meet modern design standards,
and should be consulted
|
|
139
|
- County required an automated stilling well throttle-back sensor for the
Shields Pump Station to protect the Wintersburg
- No County permit and no such sensor is planned for the Slater Pump
Station
- The Slater Pump Station should be held to the same modern safety
standards as the Shields Pump Station!
|
|
140
|
- Parkside adds to runoff in Slater Channel, so the pump station will be
expanded…
- …but the County may require throttle-back limits to protect the
Wintersburg Channel from overflowing
- Therefore if the Wintersburg is full, the new Slater pumps may not
operate, thus increasing the risk of a Slater Channel flood which is not
analyzed by the EIR
|
|
141
|
|
|
142
|
|
|
143
|
- Parkside runoff north of the Wintersburg will be sent south to the
Slater Channel
- Existing Slater neighborhoods will be at risk during El Nino-class
storms at Wintersburg high tide
- Shifting the risk burden to other neighborhoods is bad public policy,
and so are single point of failure designs!
|
|
144
|
- No discussion of the MUCH simpler solution of building a new pump
station at Lot O and directly connecting to the Wintersburg Channel
- All costs whatsoever could be funded by an Improvement District
|
|
145
|
- Seawater intrusion already a problem
- Paving this property will greatly reduce aquifer recharge from fresh
rainwater
- Seawater intrusion will then worsen
- Orange County aquifers currently significantly overdrawn due to drought
and population increase
|
|
146
|
- Parkside will sit at significantly higher elevation than adjacent
Kenilworth tract
- If there is failure of any component of the Parkside drainage system
(i.e. clogged drains, etc), flood conditions will compound for the
Kenilworth homes and surroundings
- EIR does not analyze or mitigate for these failure conditions
|
|
147
|
|
|
148
|
|
|
149
|
|
|
150
|
|
|
151
|
|
|
152
|
|
|
153
|
|
|
154
|
- Shea insists these techniques are time-tested and won’t harm adjacent
homes
- HB has history of residential subsidence problems
- Shea promises careful monitoring, but the first signs of trouble may be
cracked foundations on Kenilworth homes
- Shea and/or HB will be held liable for any problems during construction
or thereafter
- If they’re so certain of their mitigation measures they should provide indemnification
for any and all casualty loss to existing homeowners
|
|
155
|
|
|
156
|
- Liquefaction can occur on any wet, uncompacted sub-strata during a
temblor
- Parkside plans propose a 50’-wide Paseo Park to mitigate vibration and
likely subsidence problems
- sloped toward 22 existing homes on Kenilworth
- they claim that ‘neither dewatering nor remedial grading will be
required…’
- made of tens of thousands of cubic yards of fill
|
|
157
|
- The wet, uncompacted sub-strata together with the new fill would be
subject to liquefaction, therefore the whole slope would be at extreme
risk for liquefaction and slumping during a temblor, endangering homes
on Kenilworth
- The Final EIR doesn’t account for this newly created and foreseeable
problem which is a likely consequence of their proposed mitigation
|
|
158
|
|
|
159
|
- Data collected during Labor Day week when many people are away on summer
vacations (and not driving on HB roads!)
- OVSD gym EIR says collecting traffic data during “typical weekday peak
commute hours” is best (this EIR was the result of a successful court
challenge)
- Holiday weeks are not “typical”!
- OVSD enrollment was still ramping up
|
|
160
|
- Some families still on vacation
- Clueless parents slow to realize school has resumed
- Incoming transfers from year-round districts with different academic
calendars
- First enrollment statistics not collected until September 27th
|
|
161
|
|
|
162
|
|
|
163
|
- The EIR proposes left-turn median striping to mitigate Graham congestion
- But drivers are already using a de-facto left-turn median of their own
creation
- So painting some extra lines in the middle of Graham won’t change
anything!
- How about conditioning for a traffic signal at Graham & Glenstone
instead?
|
|
164
|
|
|
165
|
- Graham Street already congested at peak periods
- Congestion will be worsened by:
- Marine View gym (in progress)
- Parkside (proposed)
- Hearthside/Fieldstone (proposed)
- “Circulation Alternative B” (exit to Bolsa Chica St) needed to reduce
the additional burden on Graham Street!
|
|
166
|
- Connection to Greenleaf proposed as “emergency only” access
- But a future City Council could open it up to through traffic, despite
100% Greenleaf opposition
- Circulation Alternative B (Bolsa Chica St) would remove the Greenleaf
temptation and provide suitable emergency access
|
|
167
|
- September 9th 2002 traffic study shows significantly more
traffic on Graham
- EIR conclusions about haul route impacts are based on stale 1996 traffic
data
- These impacts of moving up to 285,000 cubic yards of fill need to be
reanalyzed
|
|
168
|
|
|
169
|
|
|
170
|
- Backups caused by the Parkside signal will create left turn delays when
exiting Kenilworth onto northbound Graham
- Southbound cars waiting at the signal will cause dangerous visibility
problems
- “Keep Intersection Clear” striping won’t solve the visibility problem
|
|
171
|
|
|
172
|
|
|
173
|
|
|
174
|
- Analyzes the potential environmental impacts
- Identifies project alternatives
- Identifies mitigation measures to lessen the project’s impacts
|
|
175
|
- “Future development of the project site may create a need for additional
fire protection services. The increase in the number of residential
units and the number of individuals brought into the area, as well as
the resulting increase in traffic will directly affect the fire
department's responses.”
- “Additional impacts to current response times are anticipated with
relocation of the [Heil] fire station.
Response time from the new location to the project site would be
greater than 5 minutes.”
- “Implementation of Mitigation Measure 1 will reduce impacts related to
the need for adequate response times and additional fire protection
services to a level less than significant.”
|
|
176
|
|
|
177
|
- No project/no development
- Development under existing zoning
- Alternative location
- Alternative park site location
- Alternative roadway connections
- Reduced density alternatives (4)
- Development incorporating the existing General Plan fire station
designation is NOT included in EIR!
|
|
178
|
- HB General Plan clearly shows the Graham/Slater area to be emergency
response deficient.
- Recent H.B.F.D. tests have not proved otherwise; so much for
“exceptional degree of overlapping coverage” from Warner, Edwards, and
“Relocated” Heil stations.
- G.P. Policy P.F. 2.1.1 “Locate fire stations in a manner which will
enable fire response times to meet a five minute standard, 80% of the
time.”
- Graham/Slater residents are just as entitled to prompt emergency service
as other residents!
|
|
179
|
|
|
180
|
- It does NOT adequately analyze the potential Public Services
environmental impacts to surrounding homes.
- It does NOT identify a project alternative incorporating a fire station.
- It does NOT identify mitigation measures to lessen the project’s
Response Time impacts to surrounding homes, nor does it identify any
medical safety mitigations.
|
|
181
|
|
|
182
|
- Car headlights on project streets will shine into Kenilworth homes
- Paseo Park will be landscaped to block this light
- But these trees won’t be planted until construction is completed in 4
years
- The trees won’t reach mature headlight-blocking heights for another 5
years
|
|
183
|
|
|
184
|
- September 9th traffic study shows substantially more existing
traffic (and thus noise) on Graham
- If the adjacent Bolsa Chica mesa cannot be used for the fill borrow
site, Graham will be used as the haul route
- EIR needs to reevaluate Graham haul route noise impacts in light of
higher traffic levels
|
|
185
|
- City construction schedule is Monday – Saturday, 7AM – 8PM
- Impacts to retirees, telecommuters, and swing shift workers,
stay-at-home moms, children and care-givers are not discussed
- The proposed mitigation measures will not reduce the impacts for these
classes of residents
|
|
186
|
- Neighborhood is under the Long Beach / Los Alamitos landing flight paths
- Military and commercial aircraft fly low enough to read tail logos
- Beach banner aircraft also present during summer months
- EIR does not factor any of this aircraft noise into its CNEL impact
calculations
|
|
187
|
|
|
188
|
|
|
189
|
- Require a secondary entrance/exit
- Require signalization of Graham & Glenstone
- Forbid the use of stop signs on “B” street to reduce noise impacts to
adjacent Kenilworth homes
- Hold Shea to their repeated promises to convey property rights to
Kenilworth / Greenleaf homeowners to give them control of access,
preventing opening of Greenleaf Lane to through traffic.
|
|
190
|
- Seeking a County permit for new storm pumps must be REQUIRED (the
current phrase “necessary permits” leaves too much wiggle room)
- Install the new pumps at Lot O for direct connect to the Wintersburg
Channel, with all costs whatsoever funded by an Improvement District
|
|
191
|
|
|
192
|
- Invalid maps at study sessions
- Missing sections from Final EIR
- Contradictory statements remain in Final EIR
- Egregious typos (“4 miles to Marine View”)
- Half-baked fire response testing
- Stale, fantasy traffic data
- Botched staff report distribution
- Staff in denial regarding County permit requirements for Slater Pump
Station
|
|
193
|
- Frequent release of significant new information as “Late Communications”
- Bob Righetti of HB DPW refusing to return e-mails and voice mails
- Dean Albright’s traffic maps withheld from agenda packet by Scott Hess
|
|
194
|
|
|
195
|
- It’s a fundamentally unbuildable wetland
- Too many negative impacts on existing neighborhoods; Existing homeowners
need better protection and indemnification against damage/loss
- Too many omitted impacts and non-mitigations in the contradictory,
error-laden, deficient Final EIR
- Fails to fulfill 7 of 10 City Goals stated in 1996 GP
|